All Hands To The Pump

By Dave Picken - August 4 2004
All Hands To The Pump
With only three weeks to go the start of the season its time to hget stuck in. The roof should be sixed this week and this will allow us to tackle a whole host of jobs .....

If you can help with any of these jobs during the week as well as at the weekend please shout up !In some kind of rough order they are:

Bar Area

  • Fix [or demolish] the cracked wall between the bar and kitchen
  • Plaster and fit a new ceiling to the bar area
  • Provide hot and cold water supply to the bar
  • Fix up electric points 
  • Install former Yuill's bar

Kitchen

  • Clean remaining fire damage
  • Install new kitchen equipment [Mark Baggs to provide units - Keith Lupton has fixed up stainless steel splashbacks]
  • Fix up separate sinks for hand washing and general use.
  • Install cooker and fridge freezer
  • Decorate

Main Room

  • Install perspex windows [Anth Carr providing perspex]
  • Install either a suspended ceiling or plasterboard ceiling
  • Rewire electric points
  • Carpet [Keith has arranged special deal with Franks Factory Flooring]
  • Fix up lighting
  • Decorate
  • Install furniture [Dave Picken has several possibilities depending on price]bar

Portakabin Extension

  • We wont have planning permission until September 8th.

Lobby

  • New front doors needed

Dressing Rooms

  • Keith and Rod will be working on them during next week.